07 Jul 2021
Since 2018, Cebarco has been constructing the Tubli wastewater treatment plant in Bahrain's capital.
The tunnel drilling work for the construction of the connecting pipe between the inlet collecting chamber and the inlet pump was completed on 5 July 2021. The pipeline is made of GRP (glass fiber reinforced plastic) pipes with 0.10m wall thickness and has the following dimensions:
Diameter 3m
Length approx. 400m
Depth approx. 25m